Sample development typically follows these stages:
|
Stage |
Description |
Estimated Time |
|
Design phase |
Concept rendering → 2D production drawings |
7-10 days |
|
3D modeling |
3D model (if required) |
5-7 days |
|
Tooling & sampling |
Tooling fabrication → sample output |
50-70 days |
|
Inspection & shipping |
Sample inspection → delivery confirmation |
7-10 days |
Total: approximately 70-100 days, depending on design complexity and tooling requirements.
Sample costs are charged at actual cost. We'll provide an accurate quote once the design plan is confirmed — so you can make a decision with a clear cost expectation.
It depends on the complexity of the project and the cooperation stage.
First batch delivery:
|
Project Type |
Estimated Timeline |
|
Existing tooling, only dial and logo changes |
Approximately 45-60 days |
|
New tooling, standard round case |
Approximately 60-75 days |
|
New tooling, complex case design |
Approximately 75-90 days |
The timeline starts from design confirmation and deposit receipt, including sample making and mass production. We'll provide an accurate delivery date once samples are confirmed.